September has been another milestone month for the Sarsfield Hall project, with visible progress and growing excitement in the community!

The framing was wrapped up this month, giving the building its full shape and structure. With the skeleton in place, the roof installation is now underway—bringing us one step closer to a weatherproof hall!

The electricians have begun running cables throughout the building, laying the groundwork for a fully powered and functional space. It’s great to see the internal systems starting to take shape.

A fresh delivery of bricks has arrived, ready to be laid in the coming weeks. This marks the beginning of the exterior transformation, and we can’t wait to see the hall’s façade come to life.

The momentum continues, and we’re pleased to say the project is ahead of schedule.